Baltic Sea – A record-breaking infrastructure project is underway beneath the Baltic Sea, where engineers are constructing the world’s longest immersed road and rail tunnel between Denmark and Germany.
Once completed, the 18-kilometre Fehmarnbelt Tunnel will slash travel times, strengthen Scandinavia’s connections to continental Europe, and serve as a critical artery for trade and mobility across the region.
The tunnel, being laid between Rødbyhavn on the Danish island of Lolland and Puttgarten in northern Germany, will replace a 45-minute ferry journey with a 10-minute drive or a 7-minute train ride.
Its completion will also reduce the train travel time between Copenhagen and Hamburg from five hours to just 2.5 hours, providing a low-emissions alternative to flying and a shortcut for freight transport.
“It’s not only linking Denmark to Germany, it’s linking Scandinavia to central Europe,” said Henrik Vincentsen, CEO of Femern, the state-owned Danish firm leading the project. “Everybody’s a winner.”
At a cost of €7.4 billion—€1.3 billion of which is funded by the European Commission—the Fehmarnbelt is among Europe’s largest infrastructure projects.
The tunnel is being constructed from north to south via a massive production site on the Danish coast, where a purpose-built factory is producing 90 enormous tunnel segments.
Each segment, or “element,” measures 217 meters in length, weighs over 73,000 tonnes, and includes five parallel tubes: two for rail, two for road, and one for emergency access.
Unlike the Channel Tunnel, which was drilled through bedrock, the Fehmarnbelt Tunnel uses an “immersed” design. This involves laying pre-fabricated segments into a trench on the seafloor with the help of underwater cameras and GPS-guided systems, achieving precision of up to 15 millimetres.
“This has never been done on this scale,” said Vincentsen. “We are breaking records.”
The project faced early resistance from German conservation groups and ferry companies, with environmental concerns raised about disruption to harbour porpoises and marine larvae. However, a German federal court dismissed these objections in 2020, clearing the path for full-scale construction.
To mitigate environmental impact, Femern is creating a 300-hectare wetland nature reserve using excavated materials. “We’ve taken strong measures to reduce the project’s footprint,” said Vincentsen.
Once operational in 2029, the tunnel is expected to accommodate more than 12,000 cars and over 100 trains daily. Toll revenues will repay the state-backed loans over the next 40 years.
In Lolland, Denmark’s poorest region, hopes are high. “The locals have been waiting for this project for years,” said construction manager Anders Gert Wede, who grew up nearby. “They’re looking forward to the jobs and new businesses it’ll bring.”
With its innovative design, monumental scale, and promise of economic transformation, the Fehmarnbelt Tunnel is poised to become a landmark of 21st-century European infrastructure.